I-70 Reconstruction (Super 70) Design/Build

Indianapolis, Indiana

American Structurepoint prepared design/build contract documents and 30- percent complete design plans for this $175 million project involving reconstruction of 6 miles of I-70, the busiest highway in Indiana. The project begins just east of the I-65 north split in downtown Indianapolis and ends just east of the I-465 interchange. Engineering services included inspection of all bridges to be rehabilitated and providing recommendations for the amount and type of work required for proper rehabilitation. The scope of work also included preparing an Engineer's Report for ramp adjustments at Keystone Avenue/Rural Street, Emerson Avenue, and Shadeland Avenue interchanges. Design work was completed in a 12-month, accelerated time period.

Read More +